DSR 2023 · SH 1

CPWD DSR item 1.3 rate analysis

Loading in or unloading cement from the railway wagons at siding and carrying the same from or into godowns adjacent to the siding, including stacking the same properly in rows upto any height as per direction of Engineer-in-charge, sweeping the wagons and screening the swept cement and filling in bags complete.

Published rate₹169.40per tonne
Rate analysis

Loading in or unloading cement from the railway wagons at siding and carrying the same from or into godowns adjacent to the siding, including stacking the same properly in rows upto any height as per direction of Engineer-in-charge, sweeping the wagons and screening the swept cement and filling in bags complete.

DSR rate₹169.40per tonne
Item code
1.3
Sub-head
SH 1
Unit
tonne
Source row
2

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of 23 tonnes of cement
LABOUR
0114 Beldar day 3.75 ₹736.00 ₹2,760.00
9999 Sundries Add for sweeping the wagon, screening the swept cement and filling the same in bags L.S. 2.62 ₹2.27 ₹5.95

Rate build-up

TOTAL ₹2,765.95
Add GST on "X" (multiplying factor 0.2127) ₹588.32
TOTAL ₹3,354.27
Add 15% CPOH on "Y" ₹503.14
TOTAL ₹3,857.41
Add Cess @ 1% on "Z" ₹38.57
Cost of 23 tonne ₹3,895.98
Cost of 1 tonne ₹169.39
Say ₹169.40